The road made from pure gold


The total cost confirmed paid so far by the Penang Government is RM209 million for consultancy fees for the 3 roads totaling 20km in length comprises of RM31.2 million for the feasibility study and RM177.5 million for the detailed design cost.
It is this RM177.5 million cost that the Board of Engineers and the Works Minister say is 400% over-priced.
In his attempt to justify this RM177.5 million in cost two day

s ago, YB Chow Kon Yeow said this fee is for a wide scope comprising of various other studies and reports – including the Detailed Environmental Impact Assessment (DEIA).
In his press-conference and statement, YB Chow Kon Yeow had claimed the cost that they paid was only 17.6% over-priced but not 400% over-priced.
However, in the 2016 Penang PAC report on the tunnel, it was specifically stated that this RM177.5 million does not include the cost of the DEIA.
In his 22nd May 2017 answer to the Penang State Assembly, Penang EXCO YB Lim Hock Seng also confirmed that a total of RM220 million have been paid and this cost specifically does not include the DEIA.
So now, the question is if YB Lim Hock Seng had misled the State Assembly or is YB Chow Kon Yeow trying to mislead the public in trying to justify a 400% overpayment?
As for the other reports and surveys listed by YB Chow Kon Yeow, the BNSC is of the opinion that many of these reports and surveys listed by are all sub-components of the feasibility study and detailed design costs, which the Penang State Government had fully paid for – and deemed way over-priced.
For example, how is it possible for you to complete a feasibility study if there was no land survey or financial feasibility study, traffic impact study done?
What kind of civil and structural engineering services would not include the land tunnel design or mechanical and electrical design architecture design?
The Penang Government should stop lying to the public and admit that the RM11 million per kilometer in pre-construction fees are highly over-priced.
Please also note that the pre-construction fees are on top of the high construction cost stated by the Penang State Government such as:
The Lebuhraya Tun Dr Lim Chong Eu to Air Itam bypass of 5.70km length costing RM851 million – or RM149 million per km
The Lebuhraya Tun Dr Lim Chong Eu to Persiaran Gurney bypass of 4km in length costing RM757.9 million – – or RM189 million per km.
Eric See-To,
https://www.facebook.com/EricSeeTo/videos/1618794868132899/ (video included)

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: